2021-11-17 Bi-weekly Meeting

Date

Nov 17, 2021

Participants

  • @Sudhakar Nallamothu

  • @Tony English

  • @Billy Chupp

  • Tom Lusco

  • Brandon P. (CDOT/WYDOT)

  • Brandon F. (SDC)

Goals

  • Discuss project status and coordination tasks among different projects

Discussion topics

Time

Item

Presenter

Notes

Time

Item

Presenter

Notes

 

V2X Hub updates

 

  • The team is working on Sprint 19 that started on Nov 3, with 17 story points planned:

    • Continuing fixing Sonar Scan memory issues for other plugins – TMX Core, TMX util and message logger plugins.

    • Continuing to work on the implementation of the global wrapper class templates for soft HSM. Implementation is almost complete.

    • ODE release testing has been completed and the PR’s were completed. ODE Release 1.2.3 is currently available.

    • V2X Hub Release 6.2 release will be available soon – this release will contain updates for the Port Drayage plugin updates.

    • Continuing to work on SET-IT to-be diagram updates.

  • We received the documentation for the 1609.2 certificates. Received 4 Raspberry PI’s last week. We sent one of them to Tony for testing. Working on one of the units and got V2X Hub installed, and will be adding 1609.2 security stack. We will be testing the units this sprint.

     

 

CARMA

 

  • Sprint 50 started on Nov 9th with testing stories for Port Drayage and TSMO UC#01 (All Way Stop)

  • Port Drayage - finished integration testing at Aberdeen and verification testing starts today at SunTrax in Florida.

  • TSMO UC#01 integration testing is in progress along with implementation of TSMO UC#02 (CDA Traffic Signal Operation).

  • Continuing to work on porting CARMA to ROS2.



WYDOT/CDOT updates




  • New ODE release is already in production in CDOT

  • New ODE release to be moved to production in WYDOT

 

SDC updates

 

  • Working on cataloging of the data.

  • Refactoring repos in terraform to make onboarding more modular

  • No truck platooning data yet.

  • Brandon F to check if SDC team has any questions about the CARMA metadata information provided last week.

  • Missing data for WYDOT feed to be uploaded today.

  • SDC Quarterly meeting to be held soon and CARMA is one of the spotlight projects presents.

Action items

A high profile demo is planned during the week of Dec 6th using the OSS4ITS reference implementation use case to demonstrate the integration of various DOT OSS products. OSS4ITS (@Jayashree Iyengar ) team will coordinate with SDC as the demo gets closer to ensure the link between OSS4ITS cloud and SDC is working.

Decisions