Deb to prioritize the 8 high priority items so that budget can be created
We need to note where we are going to be reusing or leveraging things from other efforts to aid budget discussions
Dockerization, security, and message support for SPaT and MAP are highest priority.
WZDx message manager and RSM messages will likely need to wait for the mod/CARMA
CARMA Cloud will convert into messages that vehicles can understand
Sudhakar will look at how these pieces fit into the integration backlog
Comms team can work on the documentation communications piece of rebranding ODE as V2X Cloud and V2X Hub as V2X Edge concurrently
There are also code changes, but it’s not high priority
Summary: ODE work first (2 5 8 ), then V2X Hub plugins which is 1 and 6 once the mod is excuted, and then security later down the line. and finish with cleanup.
ODE pushing messages to V2X Hub should be highest medium priority item
TIM message is one part
Probe is one part
More likely to be an epic than a story
ODE not talking to the RSU when a V2X Hub is present to avoid duplication of messages